Create a Risk-Adjusted Schedule Based on Risk Inputs
Creating scenarios based on risk inputs is useful when needing to re-calibrate a schedule based on the project's team uncertainty rankings.
To create a risk-adjusted schedule based on risk inputs, complete the following steps:
- Select the S3 // Risk tab.
- With the project selected in the Projects pane, in the Analysis group, click Build Scenario.
- Select Scenario Based on Risk Inputs, then select either PERT or Distribution Median.
- In the Analysis group, click Run Risk Analysis.
Parent Topic: Risk-Adjusted Schedule Procedures
Related concepts
Related tasks